The Village is currently in the midst of doing repaving and curbing of many streets. This year $1.5 million was allocated toward road work, and summer is the time the work is done. We asked Village Engineer Dave Goessel for the schedule of road work for this week and below is what he shared.
This is in addition to the closure of Walworth between Fenimore Road and Greenacres Avenue where a gas pipeline is being installed by Con Edison.
Here is the road resurfacing schedule confirmed with the contractor. Avoid these streets if possible!
Tuesday, August 24th
Road Resurfacing 8:00 AM to 5:00 PM
Balance of Fenimore Road, Oakstwain Road, begin Brewster Road (Fenimore toward Sage Terrace)
Wednesday, August 25th
Road Resurfacing 8:00 AM to 5:00 PM
Balance of Brewster Road, Sage Terrace, Donellan Road,
Thursday, August 26th
Road Resurfacing 8:00 AM to 5:00 PM
Brite Avenue (Fenimore to Huntington), Huntington Ave (Brewster to Montrose)
Friday, August 27th
Road Resurfacing 8:00 AM to 5:00 PM
Completion of all roads if necessary.
The schedule is weather dependent and may be adjusted accordingly for rain.