Wednesday, May 08th

Economies Proposed to Reduce Cost of Library Renovation

libraryentryProponents of a revamp of the Scarsdale Libray returned to Village Hall on Tuesday July 20 to present a more economical plan for the renovation and enhancement of the facility. In response to concerns about the price tag of the original proposal, the committee worked with their architects, engineers and village staff to identify economies that would not compromise the programmatic goals while reducing the amount of funding needed from the Village.

The plans involve renovations to all the existing interior spaces and expansions around the perimeter to allow the library to be integrated with its park-like setting. Wiring and equipment for state-of-the art technology will be installed to allow users to collaborate, do research and access new media. The entry will become a glass lobby and café where users can chat, relax and enjoy a snack or light meal. The new configuration will include several flexible meeting rooms and small group study rooms. The children's wing and children's program room will be updated and there will be a separate teen room as well. The main reading rooms will be encased in glass allowing users to look out onto library pond. The current reference room will be a quiet reading room with comfortable seating. Those who work from the library will have access to a technology suite with a printer, copier, laminator and other equipment to accommodate hands-on projects.

The original numbers called for the Village to contribute $12 million toward the $20.5 million renovation and expansion. Though the new plans were appealing, some residents feared the additional tax burden resulting from increased debt payments by the Village. At the time, Treasurer Mary Lou McClure said that borrowing $12 million would raise the Village's debt payments by $1 million a year or an average of $150 per household for 15 years.

After discussions with the trustees, the committee went back to work and identified $3 million in modifications to the project, to reduce the Village's share to $8.4 million. The Board hopes that some of these items can be funded at a later date, but believes that the changes will not "gut the project."

A complete list of the reductions and the rationale for each can be found on the Village website, but here is a summary:

One of the larger cost savings is the elimination of the basement under the new portions of the building Instead, the new portions of the building will be constructed on a slab. This will save $348,000. Another $348,000 in savings will be achieved by using less expensive flooring. Landscaping will be cutback, saving $155,000 and the outdoor reading deck will also be eliminated, for a savings of $53,000.

Original plans called for the Scott Room to be flexible space that could be partitioned to accommodate multiple groups or meetings. The reduced plan eliminates the partitions and the need for additional AV equipment, saving $227,000.

The new plan calls for less expensive furniture, shelving units and light fixtures, and also eliminates the furniture for the outdoor deck, saving $340,000.

What else? Reductions for AV equipment will save $299,735, modifications to the acoustic ceiling and architectural woodwork will result in $124,000 in savings and $150,000 will be saved by a redesign of the foundation.

Two environmental features will also be cut from the job including the solar panels on the roof, saving $459,000 and the green roof, for $53,000.

In total, savings add up to $3,009,513 including $391,000 in construction management and administration fees.

To compensate for the loss of space in the basement, 1,800 square feet of space has been added to the main level on the northwest side of the building. Architect Daniel Heuberger from Dattner Architects, called this addition, "more or less of swap of the space," and said decisions would be made down the road about its use. The new library would be 31,000 square feet, plus 1,800 square feet for the additional room.

Therefore, the estimate for the total project has been reduced from $20.5 million to $17.9 million, which includes $700,000 for the temporary library space at Supply Field.

The Library Board has pledged to raise $7.5 million in private funding, and says that many are waiting to make their donations until they know that the Village is on board. The Village will apply to receive $500,000 in grant funding for the temporary library from the NYS Dormitory Authority and also believe that they will save $1.5 million in operating costs while the library is being built.

There was discussion about the amount of funding the Village would need to bond. The Village Treasurer said that the $1.5 million in anticipated operating expense savings could not be considered "revenue." She estimated that if the Village borrowed $10 million for 15 years, total debt service would increase from about $2.8 million a year to $3.5 million a year. This would translate into taxes of $118 per year for 15 years for a household with an assessment of $1.5mm.

Temporary Library at Supply Field

Architect John D'Angelo presented plans to build a temporary library on the second floor of in the building at Supply Field. Village managers examined the use of the Supply Field building vs. the former Body Fit space on Scarsdale Avenue and determined that it made more sense to do modest renovations to the second floor of the Supply Field Building. This way, no rent would be paid, and the renovated space could be used by the Village for another purpose after the library reopens.

D'Angelo explained that the following work would be done:

  • Install heating and air conditioning and insulate the walls
  • Build a circulation desk and create offices for the library's administrative staff
  • Add toilets
  • Build a small children's area, reading area and space for copy machines and office equipment.

The overall cost to renovate the temporary library is estimated to be $700,000.

There are 40 parking spaces at Supply Field, and Library Director Elizabeth Bermel explained that the temporary library would work around field use schedules, and be open when the ball fields are not in use. Program could be held outside and in other village facilities, schools and houses of worship.

At the conclusion of the presentation, Trustee Marc Samwick asked questions about the accuracy of the financial estimates. He said, "What if we get to the end of design development and can't build what we planned; what will we do next?

Heuberger said we "never can tell that we are going to hit it on the money. But between contingencies and deduct alternatives we feel we have enough control over the project." He explained, that if needed, "we could take away the bells and whistles," and "defer items that can't be purchased to a later date." However, he assured Samwick, "you would still have a functioning library."

M.L. Perlman, who serves on the Scarsdale Forum, asked the Board and architects to consider LEED certification and requested that the solar roof be put back into the project. Simon replied, saying that there are environmentally responsible elements of the design, but it will not be LEED certified. She cited better energy conservation, rain gardens, new systems, and energy conserving windows." Heuberger added, "You don't need LEED certification to be a sustainable design. We will meet state energy code and deliver a healthy building that is economical to operate. LEED is not the only path to sustainability."

Concluding a two and a half hour meeting, the trustees thanked the board and Village managers and agreed to continue the discussion. See the proposal here.

Leave a Comment

Share on Myspace